Project Milestones

There are many crucial steps that need to be taken before a highway can be built. From traffic surveys and environmental reports to engaging stakeholders and appointing contractors and consultants. Here are the milestones in the DASH project.

17 March 2017

Launching of #contactlahkami

06 December 2016

Launch of CB4 Package

25 August 2015

Pre Qualification and Tender Exercise

DASH received the approval to acquire land for the purpose of constructing the highway under the Section 8, Land Acquisition Act 1960.
14 March 2014

2014: Public Opinion Survey and Soil Investigation Works

Apart from on-going public consultations, a Public Opinion Survey was also carried out along affected areas from 14 February to 14 March 2014. Soil investigation works […]
25 September 2013

September 2013: CA Signing

The Concession Agreement was signed on 25 September 2013. The signing signifies that PROLINTAS has been officially commissioned to build DASH under the build-operate-transfer concept. The […]
01 April 2011

April 2011 – September 2013: Preliminary Design & Negotiation, and Approvals

DASH received the Approval in Principle from UKAS for the construction of the Damansara-Shah Alam Elevated Expressway on 1 April 2011. The team then began conceptual […]